Offshore Wind Farm Project off the coast of Happo Town and Noshiro City, Akita Prefecture : Scoping Document open for public from Sep.25
Offshore Wind Farm Project off the coast of Happo Town and Noshiro City, Akita Prefecture
Project area Akita Pref. Happo town and Noshiro city offshore
Developers TEPCO Renewable Power, Incorporated
Capacity 390,000kW
Schedule Construction 2028-2029
Commercial production 2030
Aomori Pref. Tsugaru city・Ajigasawa town offshore windfarm project: Scoping Document open for public from Sep. 1
Aomori Pref. Tsugaru city・Ajigasawa town offshore windfarm project
Project area Aomori Pref. Tsugaru city, Nishi-Tsugaru county Ajigasawa town offshore
Developers Aomori south offshore windfarm LLC
Capacity 650,000kW
Schedule construction about 3years
Oga city, Katagami city and Akita city offshore windfarm project: Scoping Document open for public from Jul. 28
Oga city, Katagami city and Akita city offshore windfarm project
Project area Akita pref. Oga city, Katagami city and Akita city offshore. Promotion Zones for the Development of Marine Renewable Energy Power Generation Facilities
Developers JERA Co., Inc.、Electric Power Development Co.,Ltd.、ITOCHU Corporation、Tohoku Electric Power Co.,Inc.
Capacity 315,000kW
Construction start : under consideration
Commercial production : 24months after construction start
Wakayama Pref. offshore project: Document on Primary EIC open for public from Jul.4
Wakayama Pref. offshore project
Project area Wakayama Pref. Mihama town, Shirahama town offshore
Developers The Kansai Electric Power Company,Incorporated、RWE Renewables Japan G.K.
Capacity 1,000,000kW
Schedule Currently under consideration
8 offshore projects at Murakami City and Tainai City offshore, Niigata Pref.
5Scoping Document 3Document on Primary EIC
Tokushima Pref. Minami town offshore project: Document on Primary EIC open for public from Jun. 16
Tokushima Pref. Minami town offshore project
Project area Tokushima Pref. Kaifu county, Minami town offshore
Developers SSE Pacifico K.K.
Capacity 420,000kW
Schedule To be considered in the future